All the infrastructure at Rivers Reach community is scheduled to be completed by early 2008.
• Roads are all rocked and ready for pavement except for Phase IV. The first layer (binder) of pavement is anticipated for early November '07, on phases I, II, IIIA, & IIIB.
• Boat docks will be completed by January of '08. Dock systems 2 & 3 are installed, and dock system 1 is being installed now.
• Club House bid packages are anticipated to be sent out to contractors by October 15, 2007 with a start date of possibly early winter '07 or early Spring of '08.
• Water system is in place. Power is anticipated for installation in late October early November of '07.
• Entrance is 90% complete. Waiting on signage, electric gates and accel/decel lanes.
Rivers Reach Community Update
Lake Eufaula
Rivers Reach Entrance Area
Rivers Reach Entrance Area
Rivers Reach Entrance Area
Lake Eufaula
Rivers Reach Road progress
Rivers Reach Entrance Area
Local Marina
State Park boat ramp
Rivers Reach Entrance Area
Ducklings at Rivers Reach
Rivers Reach Entrance Area